Inverter as System Manager: Commissioning Procedure


This section describes the procedure for commissioning the SMA Commercial Storage Solution with a Sunny Tripower Storage X as System Manager.

It provides an overview of the steps, which must be performed in the prescribed sequence.

Procedure

See

For systems with more than four Sunny Tripower Storage X systems, make an appointment for a CMV measurement. Contact the Service.

CMV Measurement)

Check that all installed components have been correctly mounted and connected.

Checking the Mounting and Connection Work)

Commission all SMA Speedwire devices that are to be subordinate to the System Manager (e.g., energy meters, inverters).

Manuals for the devices

If there is more than one battery cabinet installed, set the address and terminator on the battery management system of each battery cabinet.

Setting the Address and Terminator)

If there is more than one battery cabinet installed, commission the secondary battery cabinet or cabinets.

Commissioning Secondary Battery Cabinets)

Start commissioning of the primary battery cabinet.

Commissioning the Primary Battery Cabinet)

Start commissioning of the individual battery cabinet.

Commissioning an Individual Battery Cabinet)

Commission the inverter that is to be configured as the System Manager.

Switching the Inverter On)

Establish a connection to the user interface of the inverter. There are various connection options to choose from for this:

  • Connection in the local network

  • Connection via Wi-Fi

Connecting to the Inverter User Interface)

If required, change the network configuration on the welcome page.

Commissioning Assistant

Carry out the configuration using the Commissioning Assistant. Select inverter as System Manager in the device configuration.

Commissioning Assistant

Make further settings if necessary:

  • Administrator registration

  • Device configuration (device name, device function)

  • Adding devices (e.g., energy meter, PV inverter)

  • Country standard

  • Meter at the grid connection point

  • Battery configuration

  • Energy management

  • Grid management services

  • Digital input

Operation)

Complete commissioning of the primary battery cabinet.

Commissioning the Primary Battery Cabinet)

Complete commissioning of the individual battery cabinet.

Commissioning an Individual Battery Cabinet)

Configure the temperature and humidity sensor.

Configuring the Temperature and Humidity Sensor)

To monitor the PV system and visualize the PV system data, register in the Sunny Portal and create the system in Sunny Portal or add devices to an existing system.

https://www.sunnyportal.com

    Also see: