Inverter as System Manager: Commissioning Procedure
This section describes the procedure for commissioning the SMA Commercial Storage Solution with a Sunny Tripower Storage X as System Manager.
It provides an overview of the steps, which must be performed in the prescribed sequence.
Procedure | See | |
---|---|---|
For systems with more than four Sunny Tripower Storage X systems, make an appointment for a CMV measurement. Contact the Service. | ||
Check that all installed components have been correctly mounted and connected. | ||
Commission all SMA Speedwire devices that are to be subordinate to the System Manager (e.g., energy meters, inverters). | Manuals for the devices | |
If there is more than one battery cabinet installed, set the address and terminator on the battery management system of each battery cabinet. | ||
If there is more than one battery cabinet installed, commission the secondary battery cabinet or cabinets. | ||
Start commissioning of the primary battery cabinet. | ||
Start commissioning of the individual battery cabinet. | ||
Commission the inverter that is to be configured as the System Manager. | ||
Establish a connection to the user interface of the inverter. There are various connection options to choose from for this:
| ||
If required, change the network configuration on the welcome page. | Commissioning Assistant | |
Carry out the configuration using the Commissioning Assistant. Select inverter as System Manager in the device configuration. | Commissioning Assistant | |
Make further settings if necessary:
| ||
Complete commissioning of the primary battery cabinet. | ||
Complete commissioning of the individual battery cabinet. | ||
Configure the temperature and humidity sensor. | ||
To monitor the PV system and visualize the PV system data, register in the Sunny Portal and create the system in Sunny Portal or add devices to an existing system. |
Also see:
- Switching the Inverter On
- Setting the Address and Terminator
- Checking the Mounting and Connection Work
- Commissioning Secondary Battery Cabinets
- Commissioning the Primary Battery Cabinet
- Commissioning an Individual Battery Cabinet
- Configuring the Temperature and Humidity Sensor
- Connecting to the Inverter User Interface
- CMV Measurement
- Operation