Procedure for commissioning as System Manager
This section describes the procedure for commissioning the SMA Storage XL Package with a Sunny Tripower Storage X as System Manager.
It provides an overview of the steps, which must be performed in the prescribed sequence.
Procedure | See | |
|---|---|---|
In systems with more than one battery cabinet: Configure the secondary battery cabinets before making the electrical connection. | Configuring secondary battery cabinets | |
For systems with more than four Sunny Tripower Storage X systems, make an appointment for a CMV measurement. Contact the Service. | ||
Check that all installed components have been correctly mounted and connected. | ||
Commission all SMA Speedwire devices that are to be subordinate to the System Manager (e.g., energy meters, inverters). | Manuals for the devices | |
Commission multiple battery cabinets and check the status on the control panel. | Commissioning multiple battery cabinets | |
Commission an individual battery cabinet and check the status on the control panel. | Commissioning an Individual Battery Cabinet | |
Commission the inverter that is to be configured as the System Manager. | ||
Establish a connection to the user interface of the inverter. There are various connection options to choose from for this:
| Connecting to the Inverter User Interface | |
If required, change the network configuration on the welcome page. | Commissioning wizard | |
Carry out the configuration using the commissioning wizard. Select inverter as System Manager in the device configuration. | Commissioning wizard | |
Make further settings if necessary:
| ||
Configure the temperature and humidity sensor. | ||
To monitor the PV system and visualize the PV system data, register in the Sunny Portal and create the system in Sunny Portal or add devices to an existing system. | ||
Also see: