Checking the Mounting and Connection Work
Qualified person
Before commissioning or during setup, perform a thorough check of all mounting and connection work. The basis for the check is DIN VDE 0100-600.
Procedure:
- Ensure that the inverter has been correctly mounted and connected.
- Ensure that the battery has been correctly mounted and connected. In particular, ensure adherence to the requirements for the installation site and the local fire protection regulations.
- If there is more than one battery cabinet: Ensure that the supplied DC distributor has been correctly mounted and connected.
- If there is more than one battery cabinet: Ensure that the address and terminator has been correctly set on the battery management system of each battery cabinet.
- Ensure that the supplied energy meter has been correctly mounted and connected (see manual for the energy meter).
- Measure the ground resistance and continuity of the grounding conductor.
- Measure the insulation resistance.
- Check the polarity between the inverter and battery.
- Ensure that the circuit breaker of the DC distributor is switched on.