Editing a string


Prerequisites:

  • You must have opened a project and planned it up to the page Configure PV system (detailed planning) or Configure system (quick planning).

  • You must have opened the visual roof planning tool.

Procedure:

  1. To change the length of a string, carry out a mouseover on the beginning or end point of the required string. The string must not be selected.
  2. Drawing mode is activated.
  3. To remove the last connected PV module from the string, click the required module.
  4. To add an unconnected PV module to the string, click the required module.
  5. To apply the changes, press Enter or click on [OK].