Connecting the string to the inverter input


Prerequisites:

  • You must have opened a project and planned it up to the page Configure PV system (detailed planning) or Configure system (quick planning).

  • You must have opened the visual roof planning tool.

Procedure:

  • Select the unconnected string and click the symbol for the required inverter input.
    or
    Select the unconnected string, select the system section from the drop-down list of the system sections of the required inverter and select the required input from the drop-down list of the inputs.