Configuring systems with medium voltage


  1. Add a new project or open an existing project.
  2. The Enter project data page will open.
  3. In the area Voltage level, select the option Medium voltage.
  4. Depending on which inverters you wish to use in the PV system, select either Decentralized inverters or Central inverters under System type.
  5. Enter a specification for the Preferred minimum nominal power ratio.
  6. Enter the desired Medium voltage.
  7. If you have selected the Decentralized inverters option, select the required output voltage of the inverters from the Inverter grid connection drop-down list.
  8. If required, enable the checkbox Carry out optimized reactive power adjustment with Integrated Plant Control.