Manually connecting PV modules to strings
Prerequisites:
You must have opened a project and planned it up to the page Configure PV system (detailed planning) or Configure system (quick planning).
You must have opened the visual roof planning tool.
Procedure:
- Select the first unconnected PV module of the string. This PV module is automatically assigned to the positive pole and drawing mode is activated.
- Select the PV modules to be connected one after the other, and click to add them.
- To complete string creation, press Enter or click on [OK].
- Alternatively, you can draw the string by clicking and holding the left mouse button. The PV modules will automatically be connected to the string by a mouseover across the middle of the PV module.
- When you release the mouse, the string is saved.
- To switch the pole assignment to the first and last PV module of the string, click in the menu Edit.