Adding charging stations


There are 3 ways to add a new charging station:

  • In menu My Sunny Design > Own charging stations

  • For projects with self-consumption: in the project on the page Define load profile

  • For energy-system projects: in the project on the page Energy system under Charging stations

Prerequisites:

  • For projects with self-consumption:

    • You must have opened a project and planned it up to the project page Define load profile.

    • E-mobility will also be planned in the project. In the E-mobility area, the option Take e-mobility into account is enabled.

  • For energy system projects:

    • You must have opened a project and planned it up to the project page Energy system.

    • E-mobility will also be planned in the project. On the project page Define scenario, the Charging stations option has been enabled in the System components area.

Procedure:

  1. In the menu My Sunny Design > Own charging stations: select [Add new charging stations].
    or
    In a project with self-consumption: On the page Define load profile in the area E-mobility, click on the button [New charging station].
    or
    In an energy system project: on the page Energy system in the graphic, select the button Charging stations.
  2. The Charging stations window will open.
  3. Enter the type of the charging station.
  4. Adjust the number of charging points of the charging station in the field Number of charging points.
  5. Enter the Maximum charging power AC of the charging station.
  6. Enter the Maximum charging power DC of the charging station.
  7. Click on [OK] To add the new charging station.