Changing the Meter Configuration
In the Meter configuration area the data are displayed that were entered during commissioning and registration of the system ( > Creating a Sunny Home Manager System in Sunny Portal)
A change is only possible under Extended configuration.

Only adjust the meter configuration for changes that are absolutely necessary
This might be the case, for example, if the grid operator demands a faster reaction for the dynamic active power limitation or for the zero feed-in (zero export). Contact your grid operator for information and observe the applicable standards and SMA manufacturer declarations.
Procedure:
- Select [Edit] on the tab for the device setting of the Sunny Home Manager.
- In the Meter configuration area in the fields Supply and feed-in as well as PV power generation, select the required feed-in and grid-supply meter as well as PV generation meter from the drop-down list.
- Select the required measuring interval from the Measuring interval internal energy meter drop-down list. Do not change the default 1000 ms unless this is required by standards (see corresponding manufacturer declarations and unit certificates).
Information: If the internal energy meter is not used as the meter, the measuring interval must be set directly on the meter (e.g. an SMA Energy Meter) used. - Enter the IP addresses of all devices (up to 3) that require this data (e.g. battery inverters, stand-alone inverters or hybrid inverters) in the input fields under Direct meter communication only if communication problems occur.
Information: If an entry was made here, the meter telegram is no longer sent as a multicast telegram as before. This might cause problems with third-party devices. - Click on [Save].