Procedure for device configuration


Qualified person

This section describes the procedure of device configuration for a charging station.

It provides an overview of the steps, which must be performed in the prescribed sequence.

Settings at point of interconnection

Explanation

See

Nominal grid voltage

Nominal value of the grid (e.g., 230 V)

( > Use of the user interface powered by ennexOS)

Maximum unbalanced load

Unbalanced load limit per national regulations (e.g., 4.6 kW in Germany). This is important for regulating the operation of single-phase and two-phase charging vehicles and the boost function.
Information: If no unbalanced load limit is required, the set value remains at 7400 W.
The PV-boost function is not available in systems with System Manager.

( > Use of the user interface powered by ennexOS)

Phase assignment

Assign line conductors in the same way as the Sunny Home Manager 2.0 or Energy Meter at the point of interconnection. Important for the integrated unbalanced load regulation function.
Information: If the charging station is to be operated in single-phase mode, select the line conductor in this step.

( > Use of the user interface powered by ennexOS)

Operation with meter at point of interconnection

Explanation

See

Select the country data set

If you select a country data set which is not valid for your country and purpose, it can cause a disturbance in the PV system and lead to problems with the grid operator.

When selecting the country data set, you must always observe the locally applicable standards and directives as well as the properties of the PV system (e.g. PV system size, point of interconnection).

If you are not sure which standards and directives are valid for your country or purpose, contact the grid operator.

( > Use of the user interface powered by ennexOS)

Nominal current of the point of interconnection

Nominal value of the selective circuit protection at the point of interconnection or at the Sunny Home Manager. Important for control to ensure power outage protection.

( > Use of the user interface powered by ennexOS)

Active power limitation fallback value, control at the point of interconnection

Fallback charging power in case of loss of communication.

( > Use of the user interface powered by ennexOS)

Charging settings

Explanation

See

Nominal active power

Ability to limit the maximum charging power, e.g., to 11 kW.

( > Use of the user interface powered by ennexOS)

Minimum charging current

According to IEC 61851, min. 6 A. Can be adjusted for the specific vehicle, e.g., to 10 A.

( > Use of the user interface powered by ennexOS)

AC current limitation

Nominal value of the miniature circuit breaker for the separate electric circuit for the charging station.

( > Use of the user interface powered by ennexOS)

Disconnection after full charge

Relevant for the Sunny Home Manager to plan and reserve charging power. Select Yes if the available power is to be provided to the other optional loads after the charging process is completed. Select No if the charging station is the only controlled load, or if prior climate control is to be used.

( > Use of the user interface powered by ennexOS)

Standby for charging process to disconnection

Time until activation of “Disconnect after full charge.” The default value is set to 15 minutes.

( > Use of the user interface powered by ennexOS)

Lock the charging cable to the charging station

Permanent locking of the charging cable to the charging station.

( > Use of the user interface powered by ennexOS)

Setting the phase switching time

From firmware version 2.7.X.R, the phase switching time between 15 and 120 seconds can be configured via the parameter "Minimum switching time relay" (Chrg.MinSwTm).

( > Use of the user interface powered by ennexOS)

Settings in the delta IT system

Explanation

See

PE ground connection

For firmware version >2.5.xx.R, the parameter Ground connection monitoring is enabled by default. In a delta IT system, grounding monitoring cannot be carried out due to the physical characteristics of this system configuration.

After startup, the SMA eCharger indicates event E-901: “PE connection missing.” Operation will not continue. Firmware version 2.5.29.R provides the option to disable ground connection monitoring.

For the parameter Ground connection monitoring, select the value No. Then restart the SMA eCharger.

( > Use of the user interface powered by ennexOS)

Peak load shaving

Explanation

See

Warning: When peak load shaving is enabled, the functions for PV-optimized charging of the SMA eCharger are only available to a limited extent. The SMA eCharger may not be able to be switched on or start a charging process. Also, be aware of the effects of peak load shaving on other controllable loads in the energy management system.

( > Use of the user interface powered by ennexOS)

    Also see: