Procedure for commissioning in secure power supply operation


Qualified person

This section describes the procedure of commissioning a charging station that is used in stand-alone mode.

Only one device in the system can be used as System Manager at a time (e.g. SMA Data Manager or a charging station as System Manager). All other devices must be configured as a subordinate device and recorded in the System Manager.

It provides an overview of the steps, which must be performed in the prescribed sequence.

Select no country data set

No country data set may be selected in the commissioning wizard.

  1. Skip this step in the commissioning wizard.

Procedure

See

Commission all SMA Speedwire devices that are to be subordinate to the System Manager (e.g. inverters).

Manual of the devices

Commission the charging station that is to be configured as the System Manager.

Commissioning the Product)

Establish a connection to the user interface of the charging station that is to be configured as System Manager. There are various connection options to choose from for this:

  • Direct connection via Wi-Fi

  • Connection via Wi-Fi in the local network

  • Connection via Ethernet in the local network

Direct connection via Wi-Fi)

Connection in the local network)

If required, change the network configuration on the welcome page. The automatic network configuration recommended by SMA Solar Technology AG via DHCP server is activated by default. Only change the network configurations if the default configuration is not suitable for your network.

Commissioning Assistant

Carry out the configuration using the Commissioning Assistant. Select Charging station as System Manager in the device configuration.

Commissioning Assistant

Make further settings if necessary (e.g., configure multifunction relay).

Operation)

To monitor the system in the Sunny Portal and view the data visually, create a user account in the Sunny Portal and create a system in the Sunny Portal powered by ennexOS or add devices to an existing system.

https://ennexOS.SunnyPortal.com

    Also see: