Multi-EVC operation
In multi-EVC operation mode, all charging stations must be connected to the utility grid on a rolling basis ( > Circuitry Overview). A system with 3 three-phase charging stations must be connected to the utility grid on a rolling basis as follows:
Three-phase charging station 1: L1, L2, L3
Three-phase charging station 2: L2, L3, L1
Three-phase charging station 3: L3, L1, L2
For example, a system with 2 three-phase charging stations and 1 single-phase charging station can be connected as follows:
Three-phase charging station 1: L1, L2, L3
Three-phase charging station 2: L2, L3, L1
Single-phase charging station 3: L3
Also see: