Export limitation with Sunny Home Manager 2.0 in accordance with Section 9 of the Renewable Energy Sources Act (EEG)
The system can implement requirements according to the technical requirements of Section 9 of the Renewable Energy Sources Act (EEG). Implementation is carried out using a smart meter gateway SMGW with a connected CLS adapter (FNN control box), which transfers control to the PV system.
You can find compatible devices at: SMA SMART HOME - Compatibility List for the Sunny Home Manager 2.0
Procedure:
- Open the menu item Grid management services under Configuration and go to Export limitation in accordance with §9 Renewable Energy Sources Act (EEG).
- Activate Implement grid operator requirements and then select [Save].
- Export limitation in accordance with Section 9 of the Renewable Energy Sources Act (EEG) is activated.
- Select [Connecting the FNN control box]. After establishing communication with the Sunny Home Manager 2.0, it is in coupling mode.
- Couple the Sunny Home Manager 2.0 with the FNN control box as per the manufacturer specifications. You have 2 minutes to do this. The SKI identification of the Sunny Home Manager 2.0 is displayed.