Export limitation with Sunny Home Manager 2.0 in accordance with Section 9 of the Renewable Energy Sources Act (EEG)


The system can implement requirements according to the technical requirements of Section 9 of the Renewable Energy Sources Act (EEG). Implementation is carried out using a smart meter gateway SMGW with a connected CLS adapter (FNN control box), which transfers control to the PV system.

You can find compatible devices at: SMA SMART HOME - Compatibility List for the Sunny Home Manager 2.0

Procedure:

  1. Open the menu item Grid management services under Configuration and go to Export limitation in accordance with §9 Renewable Energy Sources Act (EEG).
  2. Activate Implement grid operator requirements and then select [Save].
  3. Export limitation in accordance with Section 9 of the Renewable Energy Sources Act (EEG) is activated.
  4. Select [Connecting the FNN control box]. After establishing communication with the Sunny Home Manager 2.0, it is in coupling mode.
  5. Couple the Sunny Home Manager 2.0 with the FNN control box as per the manufacturer specifications. You have 2 minutes to do this. The SKI identification of the Sunny Home Manager 2.0 is displayed.