Requirements for Limiting of the Active Power Feed-In


Observe the following requirements for the configuration of the limiting of the active power feed-in Configuring Limitation of Active Power Feed-In):

Requirements

Setting

The grid operator requires a limitation to a percentage of the nominal system power.

Select % of PV array power and enter the required percentage.

The grid operator requires a limitation to a maximum active power in kW.

Select max. xx kW and enter the maximum permitted active power in kW.

The grid operator requires limiting of the active power feed-in to 0% or 0 kW ("zero export").

Select the option button Zero Export.

If you have activated the zero export function, also observe:

Requirements

Setting

If your system has a battery or hybrid inverter, and you have set the nominal system power to a correspondingly low value, you can use the surplus energy to charge the battery-storage system.

Activate Including the battery inverter.