Requirements for Limiting of the Active Power Feed-In
Observe the following requirements for the configuration of the limiting of the active power feed-in ( > Configuring Limitation of Active Power Feed-In):
| Requirements | Setting | 
|---|---|
| The grid operator requires a limitation to a percentage of the nominal system power. | Select % of PV array power and enter the required percentage. | 
| The grid operator requires a limitation to a maximum active power in kW. | Select max. xx kW and enter the maximum permitted active power in kW. | 
| The grid operator requires limiting of the active power feed-in to 0% or 0 kW ("zero export"). | Select the option button Zero Export. | 
If you have activated the zero export function, also observe:
| Requirements | Setting | 
|---|---|
| If your system has a battery or hybrid inverter, and you have set the nominal system power to a correspondingly low value, you can use the surplus energy to charge the battery-storage system. | Activate Including the battery inverter. | 