Checking the Mounting and Connection Work
Qualified person
Before commissioning or during setup, perform a thorough check of all mounting and connection work. The basis for the check is DIN VDE 0100-600.
Procedure:
- Ensure that the inverter has been correctly mounted and connected.
- Ensure that the battery has been correctly mounted and connected. In particular, ensure adherence to the requirements for the installation site and the local fire protection regulations.
- If there is a DC distributor present: Ensure that the DC distributor has been correctly mounted and connected.
- Ensure that all battery cabinets have been mounted correctly.
- With a single battery cabinet: Ensure that all electrical connections on the battery cabinet have been established.
- With multiple battery cabinets: Ensure that only the grounding is connected on the battery cabinets, and that no other electrical connections have been made. The connections will first be made during the commissioning process.
- Ensure that the energy meter has been correctly mounted and connected (see manual for the energy meter).
- Measure the ground resistance and continuity of the grounding conductor.
- Measure the insulation resistance.
- Check the polarity between the inverter and battery.
- With a DC distributor present: Ensure that the circuit breaker of the DC distributor is switched on.
Also see: