Mounting Procedure


This section describes the procedure for mounting the components of an SMA Storage XL Package.

It provides an overview of the steps, which must be performed in the prescribed sequence.

Procedure

See

Preparing for inverter installation and connection

Preparing for mounting and connection)

Mounting the Inverter

Mounting the Inverter)

Unpack the battery cabinet near the installation site

Unpack the battery cabinet)

Install the battery cabinet

Positioning the battery cabinet

Mount the energy meter (not included in the scope of delivery)

See manual for the energy meter

If a DC distributor (DC Combiner Box) is present, mount the DC distributor

Mounting the DC Distributor)