Procedure for commissioning as a subordinate device
This section describes the procedure for commissioning the SMA Storage XL Package with a Sunny Tripower Storage X as a subordinate device.
It provides an overview of the steps, which must be performed in the prescribed sequence.
Procedure | See | |
|---|---|---|
For systems with more than four Sunny Tripower Storage X systems, make an appointment for a CMV measurement. Contact the Service. | CMV Measurement | |
Check that all installed components have been correctly mounted and connected. | Checking the Mounting and Connection Work | |
Commission the battery. Here, a distinction is made between a single battery cabinet and multiple battery cabinets. | ||
Commission the inverter. | ||
Establish a connection to the user interface of the inverter. There are various connection options to choose from for this:
| Connecting to the Inverter User Interface | |
If required, change the network configuration on the welcome page. | Commissioning Assistant | |
Carry out the configuration using the commissioning wizard. When doing so, select inverter as Subordinate device in the device configuration. | Commissioning Assistant | |
Register the inverter as an SMA Speedwire device in the System Manager. | Commissioning Assistant of the System Manager | |
To monitor the PV system and visualize the PV system data, register in the Sunny Portal and create the system in Sunny Portal or add devices to an existing system. | ||