Procedure for commissioning as a subordinate device


This section describes the procedure for commissioning the SMA Storage XL Package with a Sunny Tripower Storage X as a subordinate device.

It provides an overview of the steps, which must be performed in the prescribed sequence.

Procedure

See

For systems with more than four Sunny Tripower Storage X systems, make an appointment for a CMV measurement. Contact the Service.

CMV Measurement

Check that all installed components have been correctly mounted and connected.

Checking the Mounting and Connection Work

Commission the battery. Here, a distinction is made between a single battery cabinet and multiple battery cabinets.

Commissioning the Battery)

Commission the inverter.

Switching the Inverter On)

Establish a connection to the user interface of the inverter. There are various connection options to choose from for this:

  • Connection in the local network

  • Connection via Wi-Fi

Connecting to the Inverter User Interface

If required, change the network configuration on the welcome page.

Commissioning Assistant

Carry out the configuration using the commissioning wizard. When doing so, select inverter as Subordinate device in the device configuration.

Commissioning Assistant

Register the inverter as an SMA Speedwire device in the System Manager.

Commissioning Assistant of the System Manager

To monitor the PV system and visualize the PV system data, register in the Sunny Portal and create the system in Sunny Portal or add devices to an existing system.

https://www.sunnyportal.com