Commissioning procedure for multiple battery cabinets


This section describes the procedure for commissioning the SMA Storage XL with multiple battery cabinets. It provides an overview of the steps, which must be performed in the prescribed sequence.

Procedure

See

Check that only the installation and grounding of the battery cabinet has been completed so far:

  • The battery cabinet is installed.

  • The grounding is connected.

  • No other electrical connections (AC, DC, CAN) have been established.

Otherwise, disconnect all connections apart from the grounding.

Checking the Mounting and Connection Work)

Configure all secondary battery cabinets.

Configuring secondary battery cabinets)

Configure the primary battery cabinet.

Configuring the primary battery cabinet with multiple battery cabinets)

Establish all electrical connections.

Electrical Connection)

Commission the battery.

Commissioning multiple battery cabinets)