Commissioning procedure for multiple battery cabinets
This section describes the procedure for commissioning the SMA Storage XL with multiple battery cabinets. It provides an overview of the steps, which must be performed in the prescribed sequence.
Procedure | See | |
|---|---|---|
Check that only the installation and grounding of the battery cabinet has been completed so far:
Otherwise, disconnect all connections apart from the grounding. | ||
Configure all secondary battery cabinets. | ||
Configure the primary battery cabinet. | ( > Configuring the primary battery cabinet with multiple battery cabinets) | |
Establish all electrical connections. | ||
Commission the battery. | ||