Commissioning multiple battery cabinets
Qualified person
Requirements:
- The inverter has been correctly mounted and connected.
- The inverter enclosure cover is securely closed.
- The battery has been mounted correctly.
- All secondary battery cabinets have been configured ( > Configuring secondary battery cabinets).
- The primary battery cabinet has already been configured ( > Configuring the primary battery cabinet with multiple battery cabinets).
- The battery has been connected correctly.
- The inverter has not yet been commissioned.
- The energy meter has been correctly mounted and connected (see manual for the energy meter).
Procedure:
- Switch on all battery cabinets ( > Switching the battery cabinet on).
- Outdoor version: Close the battery cabinet door.
- Log into the primary battery cabinet control panel as Operator. Log in is performed by clicking on the username at top left. You will receive the password following participation in the certification training.
- Select Home to the left in the menu ribbon.
- Click on the image under Battery Status Overview.
- Check that all battery cabinets are connected.
- Once all battery cabinets have been connected, commission the inverter.