Commissioning multiple battery cabinets


Qualified person

Requirements:

Procedure:

  1. Switch on all battery cabinets Switching the battery cabinet on).
  2. Outdoor version: Close the battery cabinet door.
  3. Log into the primary battery cabinet control panel as Operator. Log in is performed by clicking on the username at top left. You will receive the password following participation in the certification training.
  4. Select Home to the left in the menu ribbon.
  5. Click on the image under Battery Status Overview.
  6. 16828300428
  7. Check that all battery cabinets are connected.
  8. 16828300812
  9. Once all battery cabinets have been connected, commission the inverter.