Commissioning the Inverter
Qualified person
Requirements:
- All circuit breakers in the AC distribution board must be open.
- All Sunny Island inverters must be connected correctly ( > Checking the Wiring).
- All Sunny Island inverters must be closed ( > Sealing and Closing the Sunny Island).
- All Sunny Island inverters must be switched off.
- The fuse switch-disconnector of the battery fuse must be closed ( > Inserting the Fuse Links in the Fuse Switch-Disconnector).
- The fuse switch-disconnector of the battery fuse must be closed ( > Inserting the Fuse Links in the Fuse Switch-Disconnector).
Procedure:
- Switching on the Sunny Island:
-
For systems with one Sunny Island, press the "On" button.
-
For systems with three Sunny Island inverters, press and hold the "On" button on the master until an acoustic signal sounds.
-
For multicluster systems, press and hold the "On" button on each master until an acoustic signal sounds.
- Establish a connection to the user interface of the inverter ( > Establishing a connection to the user interface).