Starting the Generator via the User Interface
The basic procedure for changing operating parameters is explained in another section ( > Changing Operating Parameters).
Requirement:
- The Sunny Island must be able to control the generator via a control cable.
Procedure:
- Select Generator > Generator.
- Set the parameter Manual generator control to Start.
- The electricity generator starts and runs until you stop it again.
- To start the generator and leave it running for one hour, perform the following steps.
Select Generator > Operation >.
Set the parameter Reason for requesting generator to Run1h.
- The generator starts. If there is no generator request after one hour, the Sunny Island stops the generator.