Starting the System
Requirements:
- All Sunny Island inverters must be switched on.
- The circuit breakers for the AC sources in the stand-alone grid must be switched off in the AC distribution board.
- The load-break switch of the PV array must be open.
Procedure:
- For systems with one Sunny Island, press the "start-stop" button on the Sunny Island until an acoustic signal sounds.
- For systems with up to three Sunny Island inverters, press and hold the "start-stop" button on the master until an acoustic signal sounds.
- For multicluster systems, press and hold the "start-stop" button on the master of the main cluster until an acoustic signal sounds.

- The inverter LED on each Sunny Island is glowing green. The Sunny Island inverters are in operation.