Checking the Function


Testing period

  • For new systems, check every week during the six months following commissioning whether error messages have been logged. This will reveal any hidden errors in the installation or configuration.

  • For all other systems, check every six months whether error messages have been logged.

Procedure:

  1. Activate the user interface of the inverter Establishing a connection to the user interface).
  2. Log in as User Logging In and Out of the User Interface).
  3. Select the menu Events.
  4. Set filter:
    • Activate Warning and Error.

    • Deactivate Information.

  5. Set the desired time period and select [Apply time filter].
  6. If error messages have been logged, eliminate the cause Event Messages).