Connecting the AC Power Cables of the Automatic Transfer Switch


Qualified person

2049531276

The AC power cables conduct the energy between the battery-backup grid and the Sunny Island (see circuitry overview in the quick reference guide "SMA FLEXIBLE STORAGE SYSTEM with Battery-Backup Function").

Requirements:

  • With each three-phase cluster, the connection of the line conductor must be prepared as follows: L1 to the master, L2 to slave 1 and L3 to slave 2. This results in a right-hand rotating magnetic field.

  • The power of the AC sources in the battery backup grid must not exceed the maximum connected power of the PV inverters in the battery backup systems ( > AC2 Connection for Utility Grid and Generator (External Energy Source)). The powers of the individual Sunny Island inverters are added to yield the total maximum power.

Procedure:

  1. Connect the power cable from X3 on the automatic transfer switch to the terminals AC2 Gen/Grid on the Sunny Island. When doing so, connect the line conductor to AC2 Gen/Grid L and the neutral conductor to AC2 Gen/Grid NTT ( > Connecting the AC Power Cable). Thread the grounding conductor through a ferrite included in the scope of delivery and connect to AC2 Gen/Grid PE ( > Connecting the Grounding Conductor).