Procedure for commissioning in systems without System Manager


Qualified person

This section describes the procedure of commissioning an inverter that is configured individually and used in systems without System Manager (e.g. SMA Data Manager or an inverter that is configured as System Manager).

It provides an overview of the steps, which must be performed in the prescribed sequence.

Procedure

See

Commission the inverter.

Commissioning the Product)

Establish a connection to the user interface of the inverter. There are various connection options to choose from for this:

  • Direct connection via Ethernet

  • Connection via Ethernet in the local network

Establishing a connection to the user interface)

Log into the user interface.

Logging Into the User Interface)

Set country data set.

Configuring the Country Data Set)

Make further inverter settings as needed.

Operation)