Procedure for commissioning in systems without System Manager
Qualified person
This section describes the procedure of commissioning an inverter that is configured individually and used in systems without System Manager (e.g. SMA Data Manager or an inverter that is configured as System Manager).
It provides an overview of the steps, which must be performed in the prescribed sequence.
Procedure | See | |
---|---|---|
Commission the inverter. | ||
Establish a connection to the user interface of the inverter. There are various connection options to choose from for this:
| ||
Log into the user interface. | ||
Set country data set. | ||
Make further inverter settings as needed. |