Setting load management without external meters
Requirements:
The user interface must be open and you must be logged in.
Procedure:
- In the navigation area, click on [LOAD MANAGEMENT].
- Under [Dynamic Load Management] > Dynamic Load Management - DLM Master/Slave select [DLM Master (With Internal DLM-Slave)].
- Under DLM External Measurement and Control Inputs>External Meter Support select [Off].
- Set the available current under EVSE Sub-Distribution Limit (L1/L2/L3) [A].
- Set the available current under Operator EVSE Sub-Distribution Limit (L1/L2/L3) [A].
- Click on [Save] to save the changes and [Restart].