Setting load management without external meters


Requirements:

  • The user interface must be open and you must be logged in.

Procedure:

  1. In the navigation area, click on [LOAD MANAGEMENT].
  2. Under [Dynamic Load Management] > Dynamic Load Management - DLM Master/Slave select [DLM Master (With Internal DLM-Slave)].
  3. Under DLM External Measurement and Control Inputs>External Meter Support select [Off].
  4. Set the available current under EVSE Sub-Distribution Limit (L1/L2/L3) [A].
  5. Set the available current under Operator EVSE Sub-Distribution Limit (L1/L2/L3) [A].
  6. Click on [Save] to save the changes and [Restart].