Checking the Secure Power Supply Operation


Requirements:

  • The socket and switch for the secure power supply operation must be connected.

  • The inverter must be commissioned.

  • Secure power supply operation must have been configured during commissioning.

  • A load must be connected to the socket for the secure power supply operation.

Procedure:

  1. Switch off the AC miniature circuit breaker.
  2. 14314240780
  3. Turn on the switch for secure power supply operation.
  4. 14314241164
  5. Check whether the load connected to the socket for secure power supply operation is turning on. This can take up to 30 seconds.
  6. If the load does not turn on, ensure that the socket and the switch for the secure power supply operation are correctly connected. If the load still fails to turn on, contact Service.
  7. Switch on AC miniature circuit breaker.
  8. Switch off the switch for secure power supply operation.