Procedure for commissioning in systems without System Manager


Qualified person

This section describes the commissioning procedure for an inverter used in systems without a System Manager (e.g., SMA Data Manager M). The commissioning is carried out via the inverter’s user interface.

It provides an overview of the steps, which must be performed in the prescribed sequence.

Procedure

See

Commission the inverter.

Switching the Inverter On)

Establish a connection to the user interface of the inverter. There are various connection options to choose from for this:

  • Direct connection via Wi-Fi

  • Connection via Wi-Fi in the local network

  • Connection via Ethernet in the local network

Establishing a Connection to the User Interface)

Log into the user interface.

Logging Into the User Interface)

Update the firmware.

Updating firmware via the user interface)

Carry out the configuration using the installation assistant and set the country data set. Then the product will begin operation.

Starting the Installation Assistant)

Make further inverter settings as needed.

Operation)