Procedure for commissioning in systems without System Manager
Qualified person
This section describes the commissioning procedure for an inverter used in systems without a System Manager (e.g., SMA Data Manager M). The commissioning is carried out via the inverter’s user interface.
It provides an overview of the steps, which must be performed in the prescribed sequence.
Procedure | See | |
---|---|---|
Commission the inverter. | ||
Establish a connection to the user interface of the inverter. There are various connection options to choose from for this:
| ||
Log into the user interface. | ||
Update the firmware. | ||
Carry out the configuration using the installation assistant and set the country data set. Then the product will begin operation. | ||
Make further inverter settings as needed. |