Event 6411


Qualified person

Event message:

  • Self-diagnosis

  • Interference device

Explanation:

The inverter has determined that the requirement (stand-alone grid formation) for grid connection is not met. There will be temporary disconnections from the utility grid on the part of the inverter as a result.

This event rarely occurs before the inverter is connected. The inverter repeats the test and then connects to the utility grid.

Corrective measures:

  • Check whether the selected country data set meets the local standards and guidelines of the electric utility company.

  • Check whether the grid voltage is in the permissible range.

  • Check whether the voltage difference between neutral conductor N and protective grounding PE is < 10 V. Check the AC installation path for loose or detached electrical connections.