Switching the Inverter On


Qualified person

  1. Switch on the AC miniature circuit breaker.
  2. Switch on the battery or the load-break switch of the battery (see documentation of the battery manufacturer).
  3. 11209623692
  4. Turn the DC load-break switch of the inverter to the position I.
  5. After 1 to 2 minutes, all 3 LEDs light up. The start-up phase begins.
  6. All 3 LEDs go out again after approximately 90 seconds.
  7. The green LED starts to flash and, if the inverter is connected via Speedwire, the blue LED also starts to flash.
  8. If the green and red LEDs flash simultaneously during initial commissioning, operation is stopped because no country data set has been set yet. For the inverter to begin operation, the configuration must be completed and a country data set must be set.
  9. If the green LED is still flashing, the conditions for activating feed-in operation are not yet met. As soon as the conditions are met, the product will start feed-in operation.
  10. If the red LED lights up, an event is displayed. Find out which event has occurred and, if necessary, initiate countermeasures.