Commissioning multiple battery cabinets


Qualified person

Requirements:

    Procedure:

    1. Switch on all battery cabinets ( > Switching the battery cabinet on).
    2. Outdoor version: Close the battery cabinet door.
    3. Select Terminal User on the primary battery cabinet control panel at top left. The Log in window will open. Use the arrow to select Operator and click on Log in. You will receive the password following participation in the certification training. After entering the password, confirm it and then click on Log in. Then, confirm again in the new window via Confirm.
    4. Select Home to the left in the menu ribbon.
    5. Click on the image under Battery Status Overview.
    6. 16828300428
    7. Check that all battery cabinets are connected.
    8. 16828300812
    9. Once all battery cabinets have been connected, commission the inverter.