Checking the Wiring


Qualified person

Ensure that you carry out all tests relevant to the system and rectify all detected problems. Tip: Tests can be documented directly in the tables. Cross out all tests not applicable.

Requirement:

Checking the Grounding

Test point

Test criterion

Ok

Enclosure opening ExtVtg

Enclosure opening is sealed with a filler plug or M20 cable gland.

The cable diameter of the cable must be 7 mm to 14 mm for an M20 cable gland.

Cable length at the ExtVtg connection

The cable length must be less than 30 m.

Conductor cross-section of the grounding conductor at the AC1 and AC2 connections

If 1 grounding conductor is connected, the conductor cross-section must be at least 10 mm². If 2 grounding conductors are connected, the cross-section of each conductor must be at least 4 mm².

The grounding conductor must be threaded through a ferrite.

Grounding conductor connection to ground

The grounding conductor must be grounded, e.g., by connection to a grounding busbar or a foundation ground electrode.

With a TN system, neutral conductor and grounding conductor connection

Ensure by measuring that there is a conductive connection between the neutral conductor and the grounding conductor.

Grounding of the battery

Ensure that the battery is not grounded unintentionally.

If the battery has been grounded intentionally, ensure that the conductor cross-section is sufficient Connecting the Grounding Conductor with a Grounded Battery).

Checking the Additional Grounding

If the battery is grounded, you must check the additional grounding on the Sunny Island.

Test point

Test criterion

Ok

Conductor cross-section for the additional grounding

The conductor cross-section must correspond to the grounding of the battery.

Connection of additional grounding

Hexagon socket screw is screwed tight (torque: 4 Nm to 5.7 Nm).

Grounding conductor connection to ground

The grounding conductors must be grounded, e.g., by connection to a grounding busbar or foundation ground electrode.

Connecting the Sunny Island Inverter

Test point

Test criterion

Ok

Enclosure opening for DC

In the cable gland M32, the diameter of the DC power cable must be 14 mm to 25 mm.

DC connection

Terminal lugs are pressed on firmly.

The bolted connection for fitting terminal lugs to the DC connection is assembled as follows: head of M8x20 screw | conical spring washer | fender washer | terminal lug | DC connection.

Terminal lugs are firmly fastened on the Sunny Island (torque: 12 Nm).

DC power cable

The maximum length of the cables from the battery via the battery fuse to the Sunny Island is 10 m.

The conductor cross-section meets the cable requirements of 50 mm² to 95 mm² (for the recommended conductor cross-section, see Section 7.4.1).

Battery fuse

Fuse links are matched to the Sunny Island.

  • SI4.4M-13: 100 A

  • SI6.0H-13: 160 A

  • SI8.0H-13: 200 A

The cable glands connected to the battery fuse are tightened with the specified torque (see manufacturer documentation).

If installed, battery current sensor

The battery current sensor can be loaded with the maximum DC current (see technical data of the battery current sensor).

Checking Connections AC1 and AC2 of the Sunny Island Inverter

Test point

Test criterion

Ok

Enclosure openings AC1 and AC2

All enclosure openings are sealed with M25 cable glands or filler plugs.

For an M25 cable gland, the cable diameter must be 9 mm to 18 mm.

AC1 and AC2 terminals

All contact areas are not insulated.

All terminal levers are in the downward position.

All cables are securely clamped.

AC power cable at connection AC1

The cables are sufficiently protected by circuit breakers.

Trip-capable circuit breakers are installed and additional type A residual-current devices have been installed.

Maximum trip-capable circuit breakers:

  • SI4.4M-13: Tripping characteristics B6

  • SI6.0H-13: Tripping characteristics B16 or C6

  • SI8.0H-13: Tripping characteristics B16 or C6

With a three-phase system, allocation of the Sunny Island inverters

The allocation of the Sunny Island inverters to the line conductors of the stand-alone grid or the Multicluster-Box results in a right-hand rotating magnetic field. The master must be assigned to L1, slave 1 must be assigned to L2, slave 2 must be assigned to L3.

Checking the Generator Connection

Test point

Test criterion

Ok

The connection cables

The conductor cross-section is sufficient for the maximum generator current.

The cables are sufficiently protected by circuit breakers.

With a three-phase off-grid system, allocation of the line conductors

The allocation of the Sunny Island inverters to the line conductors of the generator results in a right-hand rotating magnetic field. The master must be assigned to L1, slave 1 must be assigned to L2, slave 2 must be assigned to L3.

Grounding

The exposed conductive part of the generator is grounded.

Checking the Control and Measuring Cables

Test point

Test criterion

Ok

Battery temperature sensor if installed

The battery temperature sensor is connected to the terminal BatTmp.

The battery temperature sensor is secured in the middle of the battery-storage system, in the upper third of the battery cell.

If installed, the control and measuring cables of the Multicluster-Box

The control and measuring cables are correctly connected (see Multicluster-Box manual).

If installed, the measuring cable of the battery current sensor

The measuring cable of the battery current sensor is connected to the terminal BatCur with the correct polarity Connecting the Battery Current Sensor in the Off-Grid System).

Control cable of the load shedding, if installed

The multifunction relay and the load-shedding contactors are correctly wired to each other Connecting Load-Shedding Contactors).

Cables at BatTemp and BatCur

The insulated conductors must be threaded through a ferrite.

The cable length for BatCur must be less than 3 m.

The cable length for BatTmp must be less than 30 m.

If cable lengths of 30 m and more are required for BatTemp, suitable lightning protection precautions must be taken.

If the battery temperature sensor and the batteries are not installed with the inverter in the same building, suitable lightning protection precautions must also be taken.

Cable at BatVtgOut and DigIn

The cable must be threaded through a ferrite.

The cable length must be less than 30 m.

If cable lengths of 30 m and more are required for BatVtgOut and DigIn, suitable lightning protection precautions must be taken.

If cables are to be laid outside for BatVtgOut and DigIn, suitable lightning protection precautions must be taken.

Checking the Wiring of the Communication Products

Test point

Test criterion

Ok

Electricity supply to communication products

The plug-in power supply units are plugged in.

The communication products are connected to an electricity supply.

Termination of the communication buses

The communication buses are connected to the first and last device in the bus.

Multicluster-Box control and measuring cable (BackupVtgCur)

The cable length must be less than 30 m.

Checking the System Devices

Test point

Test criterion

Ok

System components

All system devices are correctly connected (see the manuals for the devices).

Ensure by measuring that all system devices are connected with the same ground potential.

AC1 connection

After the system-specific connection, the required components are connected at terminal AC1 (see Installation - Quick Reference Guide of the System Used).

AC2 connection

After the system-specific connection, the required components are connected at terminal AC2 (see Installation - Quick Reference Guide of the System Used).