Starting the Generator via the User Interface


The basic procedure for changing operating parameters is explained in another section Changing Operating Parameters).

Requirement:

  • The Sunny Island must be able to control the generator via a control cable.

Procedure:

  • Request generator unlimited.

  • Request generator for 1 hour.

Request generator unlimited

  1. Select Generator > Generator.
  2. Set the parameter Manual generator control to Start.
  3. The electricity generator starts and runs until you stop it again.

Request generator for 1 hour

  1. Select Generator > Operation >.
  2. Set the parameter Reason for requesting generator to Run1h.
  3. The generator starts. If there is no generator request after 1 hour, the Sunny Island stops the generator.