Connecting the Measuring Cable of the Multicluster-Box 12


Qualified person

Requirements:

  • The inverters to be connected must be Sunny Island 6.0H / 8.0H inverters.
  • The utility grid must be connected to the multicluster system (see Multicluster-Box 12 operating manual).

Procedure:

  1. On every Sunny Island of the main cluster, connect the measuring cable for voltage monitoring of the Multicluster-Box 12 to the ExtVtg terminal Connecting ExtVtg):
    • On the master, connect the X112 3 and X112 4 conductors to ExtVtg.

    • On slave 1, connect the X112 7 and X112 8 insulated conductors to ExtVtg.

    • On slave 2, connect the X112 9 and X112 10 insulated conductors to ExtVtg.

  2. At the master, connect the AC contactor monitoring Connecting BatVtgOut, DigIn, BatTMP and BatCur):
    • Connect the master BatVtgOut- with the DigIn-.

    • Thread both insulated conductors through a ferrite included in the scope of delivery.

    • Connect the insulated conductor from X113 3 to BatVtgOut+.

    • Connect the insulated conductor from X113 4 to DigIn+.