Checking the Mounting and Connection Work
Qualified person
Before commissioning or during setup, perform a thorough check of all mounting and connection work. The basis for the check is DIN VDE 0100-600.
Prerequisite:
Make sure that all batteries were correctly mounted and connected.
Procedure:
- Measure the ground resistance and continuity of the grounding conductor.
- Measure the insulation resistance.
- Check the polarity between the inverter and battery.