Checking the Mounting and Connection Work


Qualified person

Before commissioning or during setup, perform a thorough check of all mounting and connection work. The basis for the check is DIN VDE 0100-600.

Prerequisite:

  • Make sure that all batteries were correctly mounted and connected.

Procedure:

  1. Measure the ground resistance and continuity of the grounding conductor.
  2. Measure the insulation resistance.
  3. Check the polarity between the inverter and battery.