Commissioning Procedure
This section describes the procedure for commissioning the SMA Home Storage.
It provides an overview of the steps, which must be performed in the prescribed sequence.
Procedure | See | |
---|---|---|
Check that all installed components have been correctly mounted and connected. | ||
If there is an SMA Home Manager installed, commission the SMA Home Manager. | Manual of the SMA Home Manager | |
Put the inverter into operation and check for the latest firmware. | Manual of the inverter | |
Start the commissioning of the battery modules. | ||
Establish a connection to the user interface of the inverter. | Manual of the inverter | |
Log into the user interface and configure the system. | Manual of the inverter | |
Check the configuration of the battery modules. | ( > Checking the configuration of the battery modules on the user interface of the inverter) |