Commissioning Procedure
Qualified person
This section describes the commissioning procedure and gives an overview of the steps you must perform in the prescribed order.

Carry out the commissioning procedure as described in the enclosure
If your product was supplied with a supplementary sheet in addition to the quick reference guide, perform commissioning according to the description in the supplementary sheet.
- Perform a firmware update before commissioning the product. You can find the update file and the manual on performing the update at the link on the supplementary sheet.

Commissioning an inverter that is captured in a communication device
When the inverter is captured in a communication device, the communication device (e.g. Sunny Home Manager) is the unit for configuring the total system. The configuration is transferred to all inverters in the system. The system password assigned via the communication device is also the password for the user interface of the inverter.
- Commission the inverter Commissioning the Inverter.
- The initial configuration of the inverter is made via the communication device. The configuration is transferred to the inverter and the settings of the inverter are overwritten.
- Deactivate the Webconnect function of the inverter via the Sunny Portal. This prevents unnecessary connection attempts of the inverter with Sunny Portal.
Procedure | See | |
---|---|---|
Commission the inverter. | Commissioning the Inverter | |
|
Establish a connection to the user interface of the inverter. There are various connection options to choose from for this:
| |
Log into the user interface. | ||
Select the inverter configuration option. | ||
Configure the product and set country data set. Then the product will begin operation. | ||
Make further inverter settings as needed. |