Electrical connection procedure
This section describes the procedure for the electrical connection of the product. It provides an overview of the steps, which must be performed in the prescribed sequence.
Procedure | See | |
---|---|---|
Ensure that the requirements for the electrical connection are fulfilled. | ||
Remove the lid. | ||
Disconnect the inverter from voltage sources. | ||
Optional: Install SMA Backup Start | Install SMA Backup Start | |
Connect the AC conductors. |
Optionally together with cables for backup operation: ( > Connect the utility grid along with power and signal cables for backup operation) | |
Connect the network cables. | ||
Optional: Connect the energy meter via RS485 | ||
Optional: Connect the battery communication cable. | ||
Optional: Connect signal source to MFR | ||
Optional: Connecting a Rapid Shutdown Initiator to the Digital Input GSI | ||
Connect the PV modules. | ||
Optional: Connect the battery power cable. |