Deactivating the Webconnect Function
Requirements:
- The PV system must be commissioned ( > Commissioning the PV System).
- A computer with an Ethernet interface must be available.
- Sunny Explorer from software version 1.06 must be installed on the computer.
Procedure:
- Access the Sunny Explorer user interface.
- Under Settings > External Communication, select the parameter Webconnect functionality switched on and set to No.
- Save settings.