Connecting the Inverter to the Utility Grid


Qualified person

Requirements:

  • The connection requirements of the grid operator must be met.

  • The grid voltage must be within the permissible range. The exact operating range of the inverter is specified in the operating parameters.

Procedure:

  1. Disconnect the AC miniature circuit breaker from all 3 line conductors and secure against reconnection.
  2. 16360804364
  3. Ensure that the DC load-break switch has been switched off and secured against reconnection.
  4. Ensure that the battery is switched off.
  5. 17333678860
  6. Remove the tool for unlocking the AC connector.
  7. 16360804748
  8. Unscrew the union nut of the AC connector.
  9. 16360805132
  10. Remove the sealing rings from the AC connector.
  11. 16947702284
  12. Pull the terminal out of the connector enclosure using the locking lever.
  13. 16947702412
  14. Insert the appropriate sealing ring based on the cable diameter.
  15. 16360805516
  16. Route the AC cable through the union nut, sealing ring, and connector enclosure.
  17. Dismantle the AC cable (60 mm).
  18. Strip off the insulation of L1, L2, L3, N, and PE (16 mm).
  19. 16360805900
  20. Insert the conductors L1, L2, L3, N, and PE into the terminal according to the labeling and tighten the terminal screws using the supplied tool (tightening torque: 2 Nm).
  21. Ensure that the conductors are correctly assigned and firmly seated in the terminal.
  22. 16360806284
  23. Insert the terminal into the connector enclosure. The terminal must snap audibly into place.
  24. 16360806668
  25. Tighten the swivel nut on the connector enclosure.
  26. 16360807052
  27. Remove the protective cap from the AC GRID socket.
  28. 16360807436
  29. Insert the AC connector into the AC GRID socket. The AC connector must snap audibly into place.