Connection Procedure for Backup Operation


Procedure

1.

Determine the operating mode (secure power supply operation or battery-backup operation).

For secure power supply operation, 1 standard commercial switch and 1 socket is required (not included in the scope of delivery)

2.

If there are multiple inverters in the system, the terminal of the automatic transfer switching device must be connected to the inverter that is configured as the System Manager. This inverter also requires a connected battery.

3.

Backup operation can be set during the commissioning of the inverter, via the settings in the user interface of the inverter or via the 360° app.