Information on Connection of the Energy Meter
Along with the energy meter, 2 electrical current transducers must be installed between the grid connection point and the feed-in point of all loads and feed-ins in the system. Observe all specifications and safety information in the energy meter manual when installing the energy meter. The energy meter is not a replacement for a revenue grade meter (RGM). The energy meter data may not be used for billing purposes. For more details, refer to the manual for the energy meter.