Operating Procedure for Grid Control
|
Event or state |
Result |
Internal transfer relay |
|---|---|---|
|
The grid management service requests the utility grid. |
– |
Open, the battery-backup grid is not connected to the utility grid. |
|
The grid voltage is within the specified thresholds for voltage and frequency. |
In order that the grid management service can detect a valid voltage, the utility grid must be within the thresholds for voltage and frequency for a minimum time. | |
|
If the grid management detects a valid voltage, the Sunny Island synchronizes the battery-backup grid with the utility grid. | ||
|
The battery-backup grid is synchronized. |
The Sunny Island connects the battery-backup grid to the utility grid. |
Closed, the battery-backup grid is connected to the utility grid. |
|
The battery-backup grid is connected to the utility grid. |
The utility grid feeds current into the battery-backup grid. | |
|
The grid management service no longer requests the utility grid. |
The Sunny Island disconnects the battery-backup grid from the utility grid and supplies the battery-backup grid. |
Open, the battery-backup grid is not connected to the utility grid. |