Generator Request Dependencies


In order to adapt the generator management system to the requirements of the off-grid system, you can change the generator request dependencies.

Generator request

Explanation

State-of-charge-dependent generator request

The generator management system requests the generator for battery charging depending on the state of charge. In this way, the battery management system prevents the battery from being discharged too deeply. Tip: You can also configure the generator request to be dependent on the time of day, e.g. to avoid starting the generator at night wherever possible.

Load-dependent generator request

If the load in the stand-alone grid exceeds a configured limit, the generator management system requests the generator. The generator then supplies the loads. This reduces the load on the battery. Where necessary, the Sunny Island and the generator supply the loads in the stand-alone grid together. The sum of the two power sources is available to the stand-alone grid.

Time-dependent generator request

You can configure on which day, at which time and for how long the generator management system requests the generator.

Charging-procedure-dependent generator request

The generator is requested for full charge and equalization charging. You can configure whether the generator is requested for full charge, equalization charge or both charging processes.