Operating Procedure with Generators without an Autostart Function
|
Event or state |
Result |
Internal transfer relay |
|---|---|---|
|
The generator management system requests the generator. |
The Sunny Island triggers a signal generator. The signal generator signals that you should start the generator. |
Open, the stand-alone grid is not connected to the generator. |
|
You start the generator (e.g. via a cable pull). |
The generator starts. | |
|
The generator voltage builds up. | ||
|
You close the load-break switch between the generator and the Sunny Island. |
The generator is connected to the Sunny Island. | |
|
The generator voltage is within the configured thresholds for voltage and frequency. |
The generator management system starts the warm-up time. | |
|
The warm-up time is running. |
– | |
|
The warm-up time ends. |
The Sunny Island synchronizes the stand-alone grid with the generator voltage. | |
|
The stand-alone grid is synchronized. |
The Sunny Island connects the stand-alone grid to the generator. |
Closed, the stand-alone grid is connected to the generator. |
|
The generator is connected. |
The generator feeds current into the stand-alone grid. | |
|
The generator management system starts the minimum run time. | ||
|
The minimum run time is running. |
Even if the generator management system no longer requests the generator, the generator remains connected to the stand-alone grid. | |
|
The minimum run time ends. |
– | |
|
The generator management system no longer requests the generator. |
The Sunny Island stops triggering the signal generator. The signal generator signals that you should disconnect the generator from the Sunny Island. | |
|
You open the load-break switch between the generator and the Sunny Island. |
The Sunny Island opens the internal transfer relay. | |
|
The Sunny Island continues to supply the stand-alone grid without interruption. | ||
|
The generator management system starts the minimum stop time. | ||
|
The minimum stop time is running. |
The Sunny Island does not detect when you restart the generator. | |
|
The generator management system cannot request the generator. The signal generator is not triggered. | ||
|
You stop the generator. |
– | |
|
The minimum stop time ends. |
The generator management system can request the generator. | |
|
The Sunny Island detects a generator start. |