Registering the Sunny Multigate in Sunny Portal


If you want to use the Webconnect function and monitor your PV system in Sunny Portal, you must register the Sunny Multigate in Sunny Portal.

Requirements:

  • The PV system must be commissioned Commissioning the PV System).
  • The Sunny Multigate must be connected to a router or modem with Internet access and must be integrated in the local network. If the router or the modem does not support DHCP, or if DHCP is deactivated, you can use the SMA Connection Assist to integrate the Sunny Multigate into your network (see www.SMA-Solar.com).
  • All UDP ports > 1024 on the router or modem must be open for outgoing connections. If there is a firewall installed on the router or modem, you might have to adjust the firewall rules.
  • It must be possible for the outgoing router or modem connections to reach all Internet destinations (target IP, target port). If there is a firewall installed on the router or modem, you might have to adjust the firewall rules.
  • On a router or modem with NAT (Network Address Translation) there must not be any port forwarding. Potential communication problems can thus be prevented.
  • There must be no packet filtering and no manipulation for SIP packets on the router or modem.
  • The registration ID (RID) and identification key (PIC) for registration in Sunny Portal must be available (see type label on the Sunny Multigate or enclosed label).

Procedure:

  • Register the Sunny Multigate in Sunny Portal (see the User Manual ""Micro Inverters in Sunny Portal"" at www.SunnyPortal.com).