Commissioning Procedure


Qualified person

This section describes the commissioning procedure and gives an overview of the steps you must perform in the prescribed order.

Procedure

See

Commission the product.

Commissioning the Product)

Establish a connection to the user interface of the product. There are various connection options to choose from for this:

  • Direct connection via WLAN

  • Connection via WLAN in the local network

  • Connection via Ethernet in the local network

Establishing a connection to the user interface)

Change the network configuration, if necessary. The automatic network configuration recommended by SMA Solar Technology AG via DHCP server is activated by default.

Changing the Network Configuration)

Carry out the configuration using the installation assistant. Make the following settings:

  • Administrator registration

  • Device configuration (settings at the point of interconnection, charging settings)

  • Product settings

  • Adding Devices (Energy Meter, Sunny Home Manager 2.0)

  • Grid management services

Configuring the Product)

To monitor the system in the Sunny Portal and view the data visually, create a user account in the Sunny Portal and create a system in the Sunny Portal or add devices to an existing system.