Commissioning Procedure


Qualified person

This section describes the commissioning procedure and gives an overview of the steps you must perform in the prescribed order.

Procedure

See

Commission the product.

( > Commissioning the Product)

Establish a connection to the user interface of the product. There are various connection options to choose from for this:

  • Direct connection via WLAN

  • Connection via WLAN in the local network

  • Connection via Ethernet in the local network

( > Establishing a Connection to the User Interface)

Change the network configuration, if necessary. The automatic network configuration recommended by SMA Solar Technology AG via DHCP server is activated by default.

( > Changing the Network Configuration)

Carry out the configuration using the installation assistant. Make the following settings:

  • Administrator registration

  • Device configuration (settings at the point of interconnection, charging settings)

  • Product settings

  • Adding Devices (Energy Meter, Sunny Home Manager 2.0)

  • Grid management services

( > Configuring the product)

To monitor the system in the Sunny Portal and view the data visually, create a user account in the Sunny Portal and create a system in the Sunny Portal or add devices to an existing system.

https://www.sunnyportal.com