Additionally Required Materials and Equipment
Materials:
|
Material |
Quantity |
Explanation |
|---|---|---|
|
Screw (diameter: maximum 10 mm) |
2 |
For attaching the wall mounting bracket |
|
Washer (diameter: maximum 30 mm) |
2 |
For attaching the wall mounting bracket |
|
If necessary, screw anchors suitable for the support surface |
2 |
For tightening the screws in the support surface |
|
Eye bolt (size: M10) |
2 |
For transporting the inverter using a crane |
|
Screw (diameter: maximum 10 mm) |
2 |
For protecting the inverter from being lifted |
|
Washer (diameter: maximum 30 mm) |
2 |
For protecting the inverter from being lifted |
|
If necessary, screw anchors suitable for the support surface |
2 |
For attaching the screws for anti-lifting lock in the support surface |
Equipment:
|
Equipment |
Quantity |
Explanation |
|---|---|---|
|
Allen key (AF 3) |
1 |
For opening and closing the lower enclosure lid and the DC protective cover and for mounting and disassembling the DC load-break switch |
|
Allen key (AF 4) |
1 |
For opening and closing the upper enclosure lid |
|
Open-end wrench (AF 15) |
1 |
For assembling the DC connectors |
|
Screwdriver (blade width: 3.5 mm) |
1 |
For removing the DC connectors |
|
Measuring device |
1 |
For verifying that no voltage is present |