Final mounting work on the MV Power Station


If the inverter is integrated into an MV Power Station with the "Grids MVT Room" or "Grids and Rodent Protection" option, the protective grids must be mounted to the medium-voltage transformer after installing the silencing baffle.

Procedure:

    14082506636
  1. Mount the protective grid for the inverter and ground strap (wrench AF13, tightening torque: 25 Nm (18.4 ft-lb)). Use the previously disassembled material.
  2. Close the door of the protective grid on the AC side of the inverter using a square wrench.