Procedure for commissioning as a subordinate device


Qualified person

This section describes the procedure for commissioning an inverter that is used in systems with Sunny Home Manager 2.0.

In systems with a System Manager, the subordinated devices are commissioned via the System Manager ( > Procedure for commissioning as System Manager).

It provides an overview of the steps, which must be performed in the prescribed sequence.

Procedure

See

Switch on the inverter.

( > Switching the Inverter On)

Establish a connection to the user interface of the inverter. There are various connection options to choose from for this:

  • Direct connection via Wi-Fi

  • Connection via Wi-Fi in the local network

  • Connection via Ethernet in the local network

See "User manual for products with a user interface powered by ennexOS"

If required, change the network configuration on the welcome page. The automatic network configuration recommended by SMA Solar Technology AG via DHCP server is activated by default. Only change the network configurations if the default configuration is not suitable for your network.

Commissioning wizard

Carry out the configuration using the Commissioning Assistant. When doing so, select Subordinate device in the device function.

Commissioning wizard

Register the inverter as an SMA Speedwire device in Sunny Home Manager 2.0.

Sunny Home Manager 2.0 commissioning wizard

    Also see: