Configuring the Energy Meter


Feed-in meters and grid-supply meters can be configured in Sunny Portal and added to a system. As a result, the energy balance of the system can be calculated and displayed. The configured energy meters are synchronized with the SMA communication device for the control at the point of interconnection.

Procedure:

  1. Select a system in Sunny Portal.
  2. Select the Meter configuration menu item in the Configuration menu.
  3. Select Device and Channel for Grid feed-in and Grid-supplied power.
  4. Click on [Save].